Considering 7'-0" x 2'-6"size door = 16.50 rft chowkat
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Partition frame (Profile) Profile: Partition frame | 17 | rft | 67 | per foot | 67 | 1139 | |
| 2 | Partition frame (Reinforcement) Re-inforcement: Partition frame | 14 | rft | 30 | per foot | 30 | 420 | |
| 3 | Steel clamp (8") Steel clamp (8") | 6 | nos | 11 | each | 11 | 66 | |
| 4 | Ordinary labour Carrying | 1 | LS | 550 | per day | 42.97 | 42.97 | |
| 5 | Carpenter Carpenter | 1 | no | 700 | per day | 700 | 700 | |
| 6 | Ordinary labour Welding in/c electricity | 1 | LS | 550 | per day | 165 | 165 | |
| Sub-Total | 2532.97 | |||||||
| Contractor's Profit | 10% | 0.1 | 253.3 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 88.65 | |||||
| Total | 2874.92 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 233.1 | ||||
| Grand Total | 3108.02 | |||||||
| Rate per rft | 188.36 | |||||||
| Rate per rm | 618.01 | |||||||