Breakup

04.5 Exposed brick works (for exterior wall without outside plaster) with automatic machine made first class bricks, very carefully laid in cement sand (F.M. 1.2) mortar (1:4) in superstructure with uniform width and depth of joints, true to vertical and horizontal lines including raking out joints, scaffolding, soaking the bricks at least for 24 hours before use, washing and screening of sand, curing at least for 7 days and high class flush pointing with cement sand (F.M. 1.2) mortar (1:1) including cost of water, electricity and other charges etc all complete and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M) In ground floor

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Automatic machine made 1st class standard bricks Bricks 1100 nos 11500 per % 0 nos 11.5 12650
2 Sand (F.M. 1.2) Sand (F.M. 1.2) in/c wastage 31 cft 1900 per % cft 19 589
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement in/c pointing 6 bags 410 per bag 410 2460
4 Head mason / Mosaic head mistry Head mason 0.5 no 800 per day 800 400
5 Mason / Mosaic mistry Mason 1.5 nos 700 per day 700 1050
6 Skilled labour Skilled labour 1.5 nos 600 per day 600 900
7 Ordinary labour Ordinary labour 2 nos 550 per day 550 1100
8 Ordinary labour Labour for soaking & cleaning bricks 2 nos 550 per day 550 1100
9 Ordinary labour washing sand 1 no 550 per day 550 550
10 Ordinary labour Labour for 7 days curing '@ 1/8 labour per day 0.875 nos 550 per day 550 481.25
11 Ordinary labour Local carriage, storage & sundries etc. 1 LS 550 per day 275 275
12 Scaffolding Scaffolding 25 sft 10 per sft 10 250
Sub-Total 21805.25
Contractor's Profit 10% 0.1 2180.53
Contractor's Overhead Expenses 3.5% 0.035 763.18
Total 24748.96
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2006.67
Grand Total 26755.63
Rate per cft 267.56
Rate per per cum 9448.88