Considering 1 swing door
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 8 mm thick PVC sheet 8 mm thick PVC sheet | 0.5 | pc | 1700 | per pc | 1700 | 850 | |
| 2 | Partition frame (Profile) Partition frame | 17 | rft | 67 | per foot | 67 | 1139 | |
| 3 | 4" New sash (Profile) 4" New sash | 20 | rft | 157 | per foot | 157 | 3140 | |
| 4 | Sliding glass bead (Profile) Sliding glass bit | 20 | rft | 21 | per foot | 21 | 420 | |
| 5 | Partition frame (Reinforcement) Partition frame | 18 | rft | 30 | per foot | 30 | 540 | |
| 6 | Rubber Rubber | 40 | rft | 7.5 | per foot | 7.5 | 300 | |
| 7 | 8 mm thick PVC sheet Screw | 0.5 | LS | 1700 | per pc | 187.74 | 93.87 | |
| 8 | Hinge Hinges | 4 | nos | 49 | per pc | 49 | 196 | |
| 9 | Sitkani Sitkani | 2 | pcs | 74 | each | 74 | 148 | |
| 10 | Handle Handle | 2 | nos | 54 | each | 54 | 108 | |
| 11 | Steel clamp (8") Steel clamp | 6 | nos | 11 | each | 11 | 66 | |
| 12 | Ordinary labour Carrying | 1 | LS | 550 | per day | 275 | 275 | |
| 13 | Carpenter Carpenter | 0.75 | nos | 700 | per day | 700 | 525 | |
| 14 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 0.75 | no | 550 | per day | 550 | 412.5 | |
| 15 | Ordinary labour Welding in/c electricity | 1 | LS | 550 | per day | 1650 | 1650 | |
| Sub-Total | 9863.37 | |||||||
| Contractor's Profit | 10% | 0.1 | 986.34 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 345.22 | |||||
| Total | 11194.93 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 907.7 | ||||
| Grand Total | 12102.63 | |||||||
| Rate per each | 12103 | |||||||
| Rate per each | 12103 | |||||||