Considering 4'-0" x 4'-0" size = 16 sft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Partition frame (Profile) Partition frame | 17 | rft | 67 | per foot | 67 | 1139 | |
| 2 | Partition glass bit Partition glass bit | 16 | rft | 11 | per foot | 11 | 176 | |
| 3 | Partition frame (Reinforcement) Partition frame | 14 | rft | 30 | per foot | 30 | 420 | |
| 4 | Rubber Rubber | 32 | rft | 7.5 | per foot | 7.5 | 240 | |
| 5 | 5 mm clear glass 5 mm clear glass | 16 | sft | 77 | per sft | 77 | 1232 | |
| 6 | Partition frame (Profile) Screw | 17 | LS | 67 | per foot | 5.52 | 93.84 | |
| 7 | Steel clamp (8") Steel clamp | 6 | nos | 11 | each | 11 | 66 | |
| 8 | Ordinary labour Carrying | 1 | LS | 550 | per day | 137.5 | 137.5 | |
| 9 | Carpenter Carpenter | 0.25 | no | 700 | per day | 700 | 175 | |
| 10 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 0.25 | no | 550 | per day | 550 | 137.5 | |
| 11 | Ordinary labour Welding in/c electricity | 1 | LS | 550 | per day | 825 | 825 | |
| Sub-Total | 4641.84 | |||||||
| Contractor's Profit | 10% | 0.1 | 464.18 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 162.46 | |||||
| Total | 5268.48 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 427.17 | ||||
| Grand Total | 5695.65 | |||||||
| Rate per sft | 356 | |||||||
| Rate per sqm | 3831.98 | |||||||