Considering 4'-0" x 4'-0"size = 16 sft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Sliding frame Profile: Sliding frame | 17 | rft | 38 | per foot | 38 | 646 | |
| 2 | Sliding sash Sliding sash | 24 | rft | 43 | per foot | 43 | 1032 | |
| 3 | Sliding glass bead (Profile) Sliding glass bead | 24 | rft | 21 | per foot | 21 | 504 | |
| 4 | Sliding interlock Sliding interlock | 7 | rft | 13.5 | per foot | 13.5 | 94.5 | |
| 5 | Sliding frame: reinforcement Re-inforcement : Sliding frame | 14 | rft | 31 | per foot | 31 | 434 | |
| 6 | Sliding sash: reinforcement Sliding sash | 20 | rft | 31 | per foot | 31 | 620 | |
| 7 | Rubber Rubber | 40 | rft | 7.5 | per foot | 7.5 | 300 | |
| 8 | Brush Brush | 30 | rft | 10 | per foot | 10 | 300 | |
| 9 | 5 mm clear glass 5 mm clear glass | 15 | sft | 77 | per sft | 77 | 1155 | |
| 10 | Ordinary labour Accessories : 1.5" screw | 1 | LS | 550 | per day | 82.5 | 82.5 | |
| 11 | Lock (2") Lock | 2 | nos | 38 | each | 38 | 76 | |
| 12 | Steel clamp (8") Steel clamp | 6 | nos | 11 | each | 11 | 66 | |
| 13 | Carpenter Others : Carpenter | 0.5 | nos | 700 | per day | 700 | 350 | |
| 14 | Ordinary labour Welding in/c electricity | 1 | LS | 550 | per day | 825 | 825 | |
| 15 | Ordinary labour Carrying | 1 | LS | 550 | per day | 137.5 | 137.5 | |
| Sub-Total | 6622.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 662.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 231.79 | |||||
| Total | 7516.54 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 609.45 | ||||
| Grand Total | 8125.99 | |||||||
| Rate per sft | 507.88 | |||||||
| Rate per sqm | 5466.82 | |||||||