Considering of =1 x 2'-6"x7'-0"= 17.50 sft work.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 16 gauge thick 50 mm x 50 mm ss hollow box 2"x2" (16 gauge ss sheet) Vertical 2 x 7'-0" = 14.00 rft Horizontal 2 x 2'-6" = 5.00 rft 19.00 rft Add wastage 5%= 0.95 rft =19.95 rft | 19.95 | rft | 320 | per ft | 320 | 6384 | |
| 2 | 16 gauge thick 50 mm x 38 mm ss hollow box 2"x1.5" (16 gauge ss sheet) Vertical 2 x 6'-10" = 13.66 rft Horizontal 2 x 2'-2" = 4.34 rft 18.00 rft Add wastage 5%= 0.90 rft =18.90 rft | 18.9 | rft | 270 | per ft | 270 | 5103 | |
| 3 | 18 gauge thick 50 mm x 12 mm ss hollow box 2.5"x1/2" (18 gauge ss sheet) louver Horizontal 2x18x 1'-10" = 65.88 rft Add wastage 5%= 3.29 rft = 69.17 rft | 69.17 | rft | 190 | per ft | 190 | 13142.3 | |
| 4 | 150 mm SS handle 6" Long 12 mm dia SS Handle | 2 | nos | 70 | each | 210 | 420 | |
| 5 | 300 mm long brass hasp bolt 12" Long 20mm dia ss hasp bolt | 1 | nos | 380 | each | 380 | 380 | |
| 6 | 100 mm longs SS hinge 4" long 20mm hinge | 3 | nos | 100 | each | 100 | 300 | |
| 7 | Clamp 6" long 3mm Clamp | 6 | nos | 40 | each | 40 | 240 | |
| 8 | Electrodes including electricity Electrode for welding | 100 | nos | 10 | each | 10 | 1000 | |
| 9 | Welder Welder | 1.5 | nos | 700 | per day | 700 | 1050 | |
| 10 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 1.5 | nos | 550 | per day | 550 | 825 | |
| 11 | Mason / Mosaic mistry i) Mason | 0.5 | nos | 700 | per day | 700 | 350 | |
| 12 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator ii) Mason helper | 0.5 | nos | 550 | per day | 550 | 275 | |
| 13 | Carriage | LS | 204.17 | |||||
| Sub-Total | 29673.47 | |||||||
| Contractor's Profit | 10% | 0.1 | 2967.35 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1038.57 | |||||
| Total | 33679.39 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2730.76 | ||||
| Grand Total | 36410.15 | |||||||
| Rate per sft | 2080.57 | |||||||
| Rate per sqm | 22395.26 | |||||||