Considering 18 rft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 225 mm dia RCC pipe Cost of machine made best quality 9" dia RCC pipe in/c all necessary fittings | 18 | rft | 270 | per foot | 270 | 4860 | |
| 2 | Sand (F.M. 0.8) Sand filling | 20 | cft | 1670 | per % cft | 16.7 | 334 | |
| 3 | Plain concrete (1:3:6) with brick chips Cement concrete(1:3:6) at 3 nos joint | 3.93 | cft | 17561.67 | % cft | 175.62 | 690.19 | |
| 4 | Mason / Mosaic mistry Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 5 | Skilled labour Skilled labour | 0.5 | no | 600 | per day | 600 | 300 | |
| Sub-Total | 6359.19 | |||||||
| Contractor's Profit | 10% | 0.1 | 635.92 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 222.57 | |||||
| Total | 7217.68 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 585.22 | ||||
| Grand Total | 7802.9 | |||||||
| Rate per rft | 433.5 | |||||||
| Rate per rm | 1422.31 | |||||||