Breakup

22.24.1 Supplying, laying, fitting & fixing best quality 225 mm dia (internal) machine made R.C.C. pipe over 100 mm thick cement concrete (1:3:6) at base and sides including single brick flat soling and gasket with cement mortar (1:4) joints, cutting and filling trenches up to required depth including excavation of soil etc. all complete in all respect as per type plan and accepted by the Engineer-in-charge (average depth of trench is 1050 mm ). (Cement: CEM-II/B-M)

Considering 18 rft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 225 mm dia RCC pipe Cost of machine made best quality 9" dia RCC pipe in/c all necessary fittings 18 rft 270 per foot 270 4860
2 Sand (F.M. 0.8) Sand filling 20 cft 1670 per % cft 16.7 334
3 Plain concrete (1:3:6) with brick chips Cement concrete(1:3:6) at 3 nos joint 3.93 cft 17561.67 % cft 175.62 690.19
4 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
5 Skilled labour Skilled labour 0.5 no 600 per day 600 300
Sub-Total 6359.19
Contractor's Profit 10% 0.1 635.92
Contractor's Overhead Expenses 3.5% 0.035 222.57
Total 7217.68
Add VAT with adjustment factor. 1.08108 7.5% 0.075 585.22
Grand Total 7802.9
Rate per rft 433.5
Rate per rm 1422.31