Considering 18 rft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 300 mm dia RCC pipe Cost of machine made best quality 12" dia RCC pipe in/c necessary fittings | 18 | rft | 460 | per foot | 460 | 8280 | |
| 2 | Sand (F.M. 0.8) Sand filling | 25 | cft | 1670 | per % cft | 16.7 | 417.5 | |
| 3 | Plain concrete (1:3:6) with brick chips Cement concrete(1:3:6) at 2 nos junctions | 4.82 | cft | 17561.67 | % cft | 175.62 | 846.49 | |
| 4 | Mason / Mosaic mistry Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 5 | Skilled labour Skilled labour | 0.75 | nos | 600 | per day | 600 | 450 | |
| Sub-Total | 10168.99 | |||||||
| Contractor's Profit | 10% | 0.1 | 1016.9 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 355.91 | |||||
| Total | 11541.8 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 935.82 | ||||
| Grand Total | 12477.62 | |||||||
| Rate per sft | 693.22 | |||||||
| Rate per sqm | 7461.82 | |||||||