Breakup

23.7.2 Add for each additional floor above ground floor

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sand (F.M. 1.2) Sand (F.M. 1.2) 5 cft 1900 per % cft 19 95
2 Sand (F.M. 2.2) Sand (F.M. 2.2) 16.67 cft 5380 per % cft 53.8 896.85
3 Ordinary Portland Cement, BDS-EN - 197-1-CEM-I ,52.5N (52.5MPa) / ASTM C-150 Type-I, 50 kg bag Cement 6.67 bags 440 per bag 440 2934.8
4 Grade 400/420(400Mpa / 400N/mm2 ≈ 60900psi/ 60 Grade), BDS-6935-2006, B400: and ratio fy to fu => 1.25 6mm dia M.S. rod 25 kg 72000 per M. ton 72 1800
5 EPS sheet (62mm thick) density 15 kg per cum 2½" EPS (density 15 x kg/m3) 21 cft 100 per cft 100 2100
6 20 mesh 24 BWG wire mesh 20 BWG galvanized (2 mesh per 25mm) 210 sft 25 per sft 25 5250
7 G.I. wire G.I. wire 1 kg 120 per kg 120 120
9 Mason / Mosaic mistry Mason 2 nos 700 per day 700 1400
10 Rod binder Rod binder 1 no 700 per day 700 700
11 Skilled labour Skilled Labour 2 no 600 per day 600 1200
12 Skilled labour Helper to rod binder 1 no 600 per day 600 600
13 Ordinary labour Ordinary labour 0.75 no 550 per day 550 412.5
14 Ordinary labour Ordinary Labour for 7 days curing 0.875 no 550 per day 550 481.25
15 Ordinary labour Local carriages, storage & sundries etc. 0.24 no 550 per day 550 132
8 Drill Bit/ Drill Machine Charge LS 50
Sub-Total 18172.4
Contractor's Profit 10% 0.1 1817.24
Contractor's Overhead Expenses 3.5% 0.035 636.03
Total 20625.67
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1672.35
Grand Total 22298.02
Rate per sft 222.98
Rate per sqm 2400.16