Breakup

24.1.1 For initial lift of 1.5 m

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Ordinary labour 10 nos 550 per day 550 5500
2 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
3 Ordinary labour Tools & plant (spade, busket) etc. 1 LS 550 per day 55 55
Sub-Total 5730
Contractor's Profit 10% 0.1 573
Contractor's Overhead Expenses 3.5% 0.035 200.55
Total 6503.55
Add VAT with adjustment factor. 1.08108 7.5% 0.075 527.31
Grand Total 7030.86
Rate per sft 70.31
Rate per sqm 756.82