Breakup

24.1.3 For additional lift of 1 m beyond 2.5 m up to 3.5 m

Considering 1000 cft of earth work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour E/W upto 5'-0" lift : (i) Ordinary labour 10 nos 550 per day 550 5500
2 Mason / Mosaic mistry (ii)Mason 0.25 no 700 per day 700 175
3 Ordinary labour (iii)Tools & plant (spade, busket) etc. 1 LS 550 per day 55 55
4 Ordinary labour (iv) Extra labour for additional lift 1.2 nos 550 per day 550 660
5 Ordinary labour Extra labour for additional lift 1.2 nos 550 per day 550 660
Sub-Total 7050
Contractor's Profit 10% 0.1 705
Contractor's Overhead Expenses 3.5% 0.035 246.75
Total 8001.75
Add VAT with adjustment factor. 1.08108 7.5% 0.075 648.79
Grand Total 8650.54
Rate per cft 8.65
Rate per cum 305.47