Considering 1000 cft of earth work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour E/W upto 5'-0" lift : (i) Ordinary labour | 10 | nos | 550 | per day | 550 | 5500 | |
| 2 | Mason / Mosaic mistry (ii)Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 3 | Ordinary labour (iii)Tools & plant (spade, busket) etc. | 1 | LS | 550 | per day | 55 | 55 | |
| 4 | Ordinary labour (iv) Extra labour for additional lift | 1.2 | nos | 550 | per day | 550 | 660 | |
| 5 | Ordinary labour Extra labour for additional lift | 1.2 | nos | 550 | per day | 550 | 660 | |
| Sub-Total | 7050 | |||||||
| Contractor's Profit | 10% | 0.1 | 705 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 246.75 | |||||
| Total | 8001.75 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 648.79 | ||||
| Grand Total | 8650.54 | |||||||
| Rate per cft | 8.65 | |||||||
| Rate per cum | 305.47 | |||||||