Considering 1000 cft of earth work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour E/W upto 5'-0" lift : (i) Ordinary labour | 10 | nos | 550 | per day | 550 | 5500 | |
| 2 | Mason / Mosaic mistry (ii)Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 3 | Ordinary labour (iii)Tools & plant (spade, busket) etc. | 1 | LS | 550 | per day | 55 | 55 | |
| 4 | Ordinary labour (iv) Extra labour for additional lift | 1.2 | nos | 550 | per day | 550 | 660 | |
| 5 | Ordinary labour (v)Extra labour for additional lift | 1.2 | nos | 550 | per day | 550 | 660 | |
| 6 | Ordinary labour (vi)Extra labour for additional lift | 1.2 | nos | 550 | per day | 550 | 660 | |
| Sub-Total | 7710 | |||||||
| Contractor's Profit | 10% | 0.1 | 771 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 269.85 | |||||
| Total | 8750.85 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 709.53 | ||||
| Grand Total | 9460.38 | |||||||
| Rate per cft | 9.46 | |||||||
| Rate per cum | 334.08 | |||||||