Breakup

24.1.5 For additional lift of 1 m beyond 4.5 m up to 5.5 m

Considering 1000 cft of earth work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour E/W upto 5'-0" lift : (i) Ordinary labour 10 nos 550 per day 550 5500
2 Mason / Mosaic mistry (ii) Mason 0.25 no 700 per day 700 175
3 Ordinary labour (iii)Tools & plant (spade, busket) etc. 1 LS 550 per day 55 55
4 Ordinary labour (iv) Extra labour for additional lift 1.2 nos 550 per day 550 660
5 Ordinary labour (v) Extra labour for additional lift 1.2 nos 550 per day 550 660
6 Ordinary labour (vi) Extra labour for additional lift 1.2 nos 550 per day 550 660
7 Ordinary labour (vii) Extra labour for additional lift 1.2 nos 550 per day 550 660
Sub-Total 8370
Contractor's Profit 10% 0.1 837
Contractor's Overhead Expenses 3.5% 0.035 292.95
Total 9499.95
Add VAT with adjustment factor. 1.08108 7.5% 0.075 770.27
Grand Total 10270.22
Rate per cft 10.27
Rate per cum 362.69