Breakup

24.1.6 For additional lift of 1 m beyond 5.5 m up to 6.5 m

Considering 1000 cft of earth work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour E/W upto 5'-0" lift : (i) Ordinary labour 10 nos 550 per day 550 5500
2 Mason / Mosaic mistry (ii) Mason 0.25 no 700 per day 700 175
3 Ordinary labour (iii)Tools & plant (spade, busket) etc. 1 LS 550 per day 55 55
4 Ordinary labour (iv) Extra labour for additional lift 1.2 LS 550 per day 550 660
5 Ordinary labour (v) Extra labour for additional lift 1.2 LS 550 per day 550 660
6 Ordinary labour (vi) Extra labour for additional lift 1.2 LS 550 per day 550 660
7 Ordinary labour (vii) Extra labour for additional lift 1.2 LS 550 per day 550 660
8 Ordinary labour (vii) Extra labour for additional lift 1.2 LS 550 per day 550 660
Sub-Total 9030
Contractor's Profit 10% 0.1 903
Contractor's Overhead Expenses 3.5% 0.035 316.05
Total 10249.05
Add VAT with adjustment factor. 1.08108 7.5% 0.075 831
Grand Total 11080.05
Rate per cft 11.08
Rate per cum 391.29