Breakup

04.11 Added cost for brick-work for each additional meter (or part of meter) free height of brick wall beyond 4 m from the respective floor in auditorium, go-down, overhead water tank etc. as description of the item No. 4.2 to 4.9 including cost of water, electricity and other charges etc. all complete and accepted by the Engineer-in-charge. (Added cost shall be incorporated in the estimate only when both sides of wall is uninterruptedly free beyond 4.0 meter)

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Head mason / Mosaic head mistry Extra head mason 0.05 no 800 per day 800 40
2 Mason / Mosaic mistry Extra mason 0.15 no 700 per day 700 105
3 Skilled labour Extra skilled labour 0.1 no 600 per day 600 60
4 Ordinary labour Extra ordinary labour 0.25 no 550 per day 550 137.5
5 Scaffolding Extra for scaffolding 12.5 sft 10 per sft 10 125
6 Ordinary labour Extra for local carriage, storage & sundries etc. 1 LS 550 per day 55 55
Sub-Total 522.5
Contractor's Profit 10% 0.1 52.25
Contractor's Overhead Expenses 3.5% 0.035 18.29
Total 593.04
Add VAT with adjustment factor. 1.08108 7.5% 0.075 48.08
Grand Total 641.12
Rate per cft 6.41
Rate per per cum 226.37