Breakup

24.3 Creating turf on the side slopes and top of embankment with good quality turf not less than 225 mm square chunk, watering till the grass grown including all leads and lifts etc. complete and accepted by the Engineer-in-charge.

Considering 1000 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Labour for cutting grass turf upto proper size, carrying and placing it on the embankment side by side : Ordinary labour 1 nos 550 per day 550 550
2 Skilled labour Skilled labour 0.5 no 600 per day 600 300
3 Ordinary labour Watering the turf properly & profusely at least twice a day and guarding it from grazing animals for 7 days : Ordinary labour 1 nos 550 per day 550 550
5 Royalty of turf Royalty or cost of the turf 1000 sft 30 per % sft 0.3 300
Sub-Total 1700
Contractor's Profit 10% 0.1 170
Contractor's Overhead Expenses 3.5% 0.035 59.5
Total 1929.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 156.45
Grand Total 2085.95
Rate per sft 2.09
Rate per sqm 22.5