Considering 1000 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Labour for cutting grass turf upto proper size, carrying and placing it on the embankment side by side : Ordinary labour | 1 | nos | 550 | per day | 550 | 550 | |
| 2 | Skilled labour Skilled labour | 0.5 | no | 600 | per day | 600 | 300 | |
| 3 | Ordinary labour Watering the turf properly & profusely at least twice a day and guarding it from grazing animals for 7 days : Ordinary labour | 1 | nos | 550 | per day | 550 | 550 | |
| 5 | Royalty of turf Royalty or cost of the turf | 1000 | sft | 30 | per % sft | 0.3 | 300 | |
| Sub-Total | 1700 | |||||||
| Contractor's Profit | 10% | 0.1 | 170 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 59.5 | |||||
| Total | 1929.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 156.45 | ||||
| Grand Total | 2085.95 | |||||||
| Rate per sft | 2.09 | |||||||
| Rate per sqm | 22.5 | |||||||