Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 1st class/Picked jhama standard bricks Bricks | 300 | nos | 10000 | per % 0 nos | 10 | 3000 | |
| 2 | Sand (F.M. 0.8) Fine sand | 5 | cft | 1670 | per % cft | 16.7 | 83.5 | |
| 3 | Head mason / Mosaic head mistry Head mason | 0.0625 | no | 800 | per day | 800 | 50 | |
| 4 | Mason / Mosaic mistry Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 5 | Skilled labour Skilled labour | 1 | no | 600 | per day | 600 | 600 | |
| 6 | Ordinary labour Local carriage, sundries, T & P | 1 | LS | 550 | per day | 275 | 275 | |
| Sub-Total | 4183.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 418.35 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 146.42 | |||||
| Total | 4748.27 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 384.99 | ||||
| Grand Total | 5133.26 | |||||||
| Rate per sft | 51.33 | |||||||
| Rate per sqm | 552.52 | |||||||