24.5.1 Brick on edges pavement in herring bone bond (HBB) with first class or picked jhama bricks as per alignment, camber and grade over 12 mm thick sand cushion (F.M. 0.80) including filling the joints with the same sand including cost of all materials and accepted by the Engineer-in-charge.

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class/Picked jhama standard bricks Bricks 500 nos 10000 per % 0 nos 10 5000
2 Sand (F.M. 0.8) Fine sand 10 cft 1670 per % cft 16.7 167
3 Head mason / Mosaic head mistry Head mason 0.0625 no 800 per day 800 50
4 Mason / Mosaic mistry Mason 0.75 no 700 per day 700 525
5 Skilled labour Skilled labour 1 no 600 per day 600 600
6 Ordinary labour Local carriage, sundries, T & P 1 LS 550 per day 412.5 412.5
Sub-Total 6754.5
Contractor's Profit 10% 0.1 675.45
Contractor's Overhead Expenses 3.5% 0.035 236.41
Total 7666.36
Add VAT with adjustment factor. 1.08108 7.5% 0.075 621.6
Grand Total 8287.96
Rate per sft 82.88
Rate per sqm 892.12