Breakup

24.6 Double brick flat soling in roadwork with first class or picked jhama bricks as per alignment, camber and grade including filling the joints with fine sand (F.M. 0.80) and also providing 12 mm thick sand cushion in between the two layers of brick flat soling with the same quality of sand including cost of all materials and accepted by the Engineer-in-charge.

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class/Picked jhama standard bricks Bricks 600 nos 10000 per % 0 nos 10 6000
2 Sand (F.M. 0.8) Fine sand 12 cft 1670 per % cft 16.7 200.4
3 Head mason / Mosaic head mistry Head mason 0.0625 no 800 per day 800 50
4 Mason / Mosaic mistry Mason 1 no 700 per day 700 700
5 Skilled labour Skilled labour 2 nos 600 per day 600 1200
6 Ordinary labour Local carriage, sundries, T & P 1 LS 550 per day 275 275
Sub-Total 8425.4
Contractor's Profit 10% 0.1 842.54
Contractor's Overhead Expenses 3.5% 0.035 294.89
Total 9562.83
Add VAT with adjustment factor. 1.08108 7.5% 0.075 775.36
Grand Total 10338.19
Rate per sft 103.38
Rate per sqm 1112.78