Breakup

04.12 Providing brick works for 200 mm x 100 mm facing in superstructure with 200 mm x 100 mm x 50 mm machine made klinker hard pressed facing bricks of approved quality with cement sand (F.M. 1.2) mortar (1:4), including racking out joints, cutting the bricks to required size wherever necessary including high class recessed pointing, cleaning and soaking the bricks at least for 24 hours before use and washing and screening of sand, necessary scaffolding, curing at least for 7 days for all floors up to 4th floor including cost of water, electricity and other charges etc. all complete and accepted by the Engineer-in-charge. (100x200 mm face should be placed for facing). (Cement: CEM-II/B-M) In ground floor

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 8" x 4" x 2"/ 200 x 100 x 50 mm machine made hard pressed klinker facing bricks 200 x 100 x 50 mm facing bricks (facing 200 x 100 mm) in/c 5% wastage 452 nos 19750 per % 0 nos 19.75 8927
2 Sand (F.M. 1.2) Sand (F.M. 1.2) in/c wastage 12 cft 1900 per % cft 19 228
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement in/c for pointing 2.26 bags 410 per bag 410 926.6
4 Head mason / Mosaic head mistry Head mason 1 no 800 per day 800 800
5 Mason / Mosaic mistry Mason 2.25 no 700 per day 700 1575
6 Skilled labour Skilled labour 1.5 no 600 per day 600 900
7 Ordinary labour Ordinary labour 1.5 no 550 per day 550 825
8 Ordinary labour Labour for 7 days curing '@ 1/8 labour per day 0.875 nos 550 per day 550 481.25
9 Scaffolding Scaffolding 25 sft 10 per sft 10 250
10 Ordinary labour Washing of sand, local carriage, storage & sundries etc. 1 LS 550 per day 275 275
Sub-Total 15187.85
Contractor's Profit 10% 0.1 1518.79
Contractor's Overhead Expenses 3.5% 0.035 531.57
Total 17238.21
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1397.69
Grand Total 18635.9
Rate per sft 186.36
Rate per per sqm 2005.98