Breakup

24.8.1 For 62 mm to 40 mm size

Considering 100 cft of work For 100 cft of works 62 mm - 40 mm size

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class/Picked jhama standard bricks Bricks 850 nos 10000 per % 0 nos 10 8500
2 Ordinary labour Ordinary labour for breaking 3.5 nos 550 per day 550 1925
Sub-Total 10425
Contractor's Profit 10% 0.1 1042.5
Contractor's Overhead Expenses 3.5% 0.035 364.88
Total 11832.38
Add VAT with adjustment factor. 1.08108 7.5% 0.075 959.38
Grand Total 12791.76
Rate per cft 127.92
Rate per cum 4517.49