Breakup

24.8.2 For 40 mm to 25 mm size

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class/Picked jhama standard bricks Bricks 850 nos 10000 per % 0 nos 10 8500
2 Ordinary labour Ordinary labour for breaking 4.5 nos 550 per day 550 2475
Sub-Total 10975
Contractor's Profit 10% 0.1 1097.5
Contractor's Overhead Expenses 3.5% 0.035 384.13
Total 12456.63
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1010
Grand Total 13466.63
Rate per cft 134.67
Rate per cum 4755.87