Considering 100 cft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 1st class/Picked jhama standard bricks Bricks | 850 | nos | 10000 | per % 0 nos | 10 | 8500 | |
| 2 | Ordinary labour Ordinary labour for breaking | 4.5 | nos | 550 | per day | 550 | 2475 | |
| Sub-Total | 10975 | |||||||
| Contractor's Profit | 10% | 0.1 | 1097.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 384.13 | |||||
| Total | 12456.63 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1010 | ||||
| Grand Total | 13466.63 | |||||||
| Rate per cft | 134.67 | |||||||
| Rate per cum | 4755.87 | |||||||