Breakup

24.10.2 Providing improved sub-grade with sand F.M.>0.80 having compacted thickness as per specification including cost of sand, carrying, local handling, spreading uniformly in layers of 150mm to proper grade camber, super elevation, rolling properly with 7-10 tone vibratory roller and watering profusely for compaction 95% MDD (Modified Proctor Test) including cost of fuel, lubricants, spares, maintenance, driver etc. all complete and accepted by the Engineer-in-charge.

Considering 21186 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sand (F.M. 0.8) Fine sand (F.M.=0.80) 23657 cft 1670 per % cft 16.7 395071.9
2 Diesel Diesel 105.93 liter 68 litre 68 7203.24
3 Lubricants Lubricants 6.35 liter 220 per litre 220 1397
4 Skilled labour Skilled labour 4 no 600 per day 600 2400
5 Ordinary labour Ordinary labour 26 no 550 per day 550 14300
6 Hire-charge of chain dozer Hire Charge of Dozer 1 day 8200 per day 8200 8200
7 Hire charge of pneumatic multiple tired roller (7 tires, 8-10 tons) Hire charge of Vibratory roller ( 7-10tonne) 1 day 5000 per day 5000 5000
8 Fuel & lubricants, spares, maintenance, driver etc. for 8-12 ton road roller. spares, maintenance, driver etc. for 7-10 ton road roller. 1 day 1500 per day 1500 1500
9 Hire charge of water tanker (truck mounted) Hire Charge of Water Tanker (Truck Mounted) 4 day 3200 per day 3200 12800
Sub-Total 447872.14
Contractor's Profit 10% 0.1 44787.21
Contractor's Overhead Expenses 3.5% 0.035 15675.52
Total 508334.87
Add VAT with adjustment factor. 1.08108 7.5% 0.075 41216.3
Grand Total 549551.17
Rate per cft 25.94
Rate per cum 916.07