24.10.6 Providing compacted aggregate base type-II ( With Pever) with graded metal of crushed well burnt picked jhama, 1st class brick chips 25mm to 38mm size and Sylhet sand F.M>1.00 @ ratio of (2:1) (Brick Khoa : Sand) having compacted thickness of 150mm including local handling spreading uniformly to proper grade and camber and super elevation, hand packing, rolling properly with 7-10 tone vibratory roller and watering profusely for proper consolidation with blending materials etc. in/c. cost of all materials complete as per direction of the Engineer-in-charge (Payment will be made on compacted volume and compaction of 98% MDD in Modified Proctor Test).

Considering 353 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sand (F.M. 0.8) Fine sand FM > 1.0 114.75 cft 1670 per % cft 16.7 1916.32
2 1st class/Picked jhama standard bricks Brick 3130 nos 10000 per % 0 nos 10 31300
3 Breaking of 12 mm (1/2") down brick chips Breaking 12mm downgraded brickchips 344.27 cft 1220 per % cft 12.2 4200.09
4 Diesel Diesel 105.93 liter 68 litre 68 7203.24
5 Mason / Mosaic mistry Mason 1 no 700 per day 700 700
6 Ordinary labour Ordinary labourer 4 no 550 per day 550 2200
7 Hire charge of dump truck/ tripping trucks Dump Truck 0.15 day 5000 per day 5000 750
8 Hire charge of Pay loader Pay Loader 0.04 day 13000 per day 13000 520
9 Hire charge of aggregate base paver Aggregate Base Paver 0.1 day 30500 per day 30500 3050
10 Hire charge of pneumatic multiple tired roller (7 tires, 8-10 tons) Vibratory roller ( 7-10tonne) 0.1 day 5000 per day 5000 500
11 Fuel & lubricants, spares, maintenance, driver etc. for 8-12 ton road roller. spares, maintenance, driver etc. for 7-10 ton road roller. 1 day 1500 per day 1500 1500
Sub-Total 53839.65
Contractor's Profit 10% 0.1 5383.97
Contractor's Overhead Expenses 3.5% 0.035 1884.39
Total 61108.01
Add VAT with adjustment factor. 1.08108 7.5% 0.075 4954.7
Grand Total 66062.71
Rate per cft 187.15
Rate per cum 6609.2