04.13 Providing brick works for 200 mm x 50 mm facing in superstructure with 200 mm x 50 mm x 50 mm machine made hard pressed klinker facing red or maroon strips of approved quality with 20 mm thick cement sand (F.M.1.2) mortar (1:4), 10 mm thick cement mortar in adjacent sides including racking out joints and cutting the bricks to required sizes wherever necessary with high class recessed pointing, cleaning and soaking the bricks for at least 24 hours before use and washing of sand, necessary scaffolding, curing at least for 7 days for all floors up to 4th floor including cost of water, electricity and other charges etc. all complete and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M) In ground floor

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 8" x 2" x 2"/ 200 x 50 x 50 mm machine made klinker facing red or maroon strips 200 x 50 x 50 mm facing bricks (facing 200 x 50 mm) in/c 5% wastage 856 nos 18000 per % 0 nos 18 15408
2 Sand (F.M. 1.2) Sand (F.M. 1.2) in/c wastage 14 cft 1900 per % cft 19 266
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement in/c for pointing 2.75 bags 410 per bag 410 1127.5
4 Head mason / Mosaic head mistry Head mason 1 no 800 per day 800 800
5 Mason / Mosaic mistry Mason 2.3333333333 nos 700 per day 700 1633.33
6 Skilled labour Skilled labour 1.5 nos 600 per day 600 900
7 Ordinary labour Ordinary labour 1.5 nos 550 per day 550 825
8 Ordinary labour Labour for 7 days curing '@ 1/8 labour per day 0.875 no 550 per day 550 481.25
9 Scaffolding Scaffolding 25 sft 10 per sft 10 250
10 Ordinary labour Washing of sand, local carriage, storage & sundries etc. 1 LS 550 per day 275 275
Sub-Total 21966.08
Contractor's Profit 10% 0.1 2196.61
Contractor's Overhead Expenses 3.5% 0.035 768.81
Total 24931.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2021.47
Grand Total 26952.97
Rate per sft 269.53
Rate per per sqm 2901.22