Breakup

24.15 25 mm thick compacted pre-mixed dense bituminous carpeting with 12 mm down graded stone-chips (having LAA value <= 30%, water absorption not greater than 2%, flakiness index not greater than 35) of gradation as specified, @ 0.35 cum of stonechips mixed with 29.8 kg heated bitumen of 60/70 penetration grade heated straight run bitumen satisfying the requirements of ASTM/AASHTO. Bitumen content % by wt. of total is 4.5% to 5.50% or as determined by job mix design. The bitumen and stone-chips shall be separately heated to a temperature of 140°C – 155°C and 150°C – 170°C respectively before mixing. The mixing shall be done at temperature between 140°C – 160°C at a separate place away from the fire. The bitumen and stone-chips mixture shall be laid uniformly over 10 sqm of surface in proper camber, grade and super-elevation only on the prepared and accepted base or surface in a single appropriate layer to give the specified compacted thickness. The mixture should be rolled with appropriate steel drum roller (3-5 tons) & pneumatic multiple tire roller (8-10 tons) to full compaction. The rolling temperature shall be maintained not below 90°C including supply of all materials, their carriage, labourers, tools and equipments etc. all complete as per direction of the Engineer-in-charge. (In order to achieve the specified grading, a blending of nominal maximum size of 20mm, 12mm crushed stone chips and stone dust is suggested and proportion will have to be determined by the laboratory analysis).

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 12 mm (1/2") down grade stone chips Cost of materials : Stone Chips (12 mm downgraded) 8.63 cft 17840 per % cft 178.4 1539.59
2 60/70 grade bitumen for road work Bitumin (60/70 grade) 61 lbs 56000 per M. ton 25.4 1549.4
3 Stone dust (2.38 mm down grade) Stone Dust (2.38 mm downgraded) 2.88 cft 5500 per % cft 55 158.4
4 Fire-wood Firewood 0.75 mnds 220 per mound 220 165
5 Mason / Mosaic mistry Labour charges: Mason 0.02 no 700 per day 700 14
6 Skilled labour Skilled labour 0.12 no 600 per day 600 72
7 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
8 Ordinary labour Sundries and T & P 1 LS 550 per day 183.33 183.33
9 Hire charge of vibratory (ride on) roller with 2 steel drum compactor (3-5 tons) Equipment Charges: Hire Charge of Vibratory (Ride On) Roller 2 Steel Drum Compactor (3-5 tons) 0.01 day 5500 per day 5500 55
10 Hire charge of pneumatic multiple tired roller (7 tires, 8-10 tons) Hire Charge of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons) 0.01 day 5000 per day 5000 50
11 Diesel Diesel 0.16 liter 68 litre 68 10.88
12 Lubricants Lubricants 0.016 liter 220 per litre 220 3.52
Sub-Total 4076.12
Contractor's Profit 10% 0.1 407.61
Contractor's Overhead Expenses 3.5% 0.035 142.66
Total 4626.39
Add VAT with adjustment factor. 1.08108 7.5% 0.075 375.11
Grand Total 5001.5
Rate per sft 50.02
Rate per sqm 538.42