Breakup

24.17 Providing tack coat @ 7.50 kg of bitumen (60/70 penetration grade) per 10 sqm including heating bitumen up to 175°C to 185°C etc. all complete (cost of bitumen included) and accepted by the Engineer-in-charge.

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 60/70 grade bitumen for road work Cost of materials : Bitumen (60/70 grade) 15.5 lbs 56000 per M. ton 25.4 393.7
2 Fire-wood Fire wood 0.2 mnds 220 per mound 220 44
3 Mason / Mosaic mistry Labour charges: Mason 0.004 no 700 per day 700 2.8
4 Skilled labour Skilled labour 0.04 no 600 per day 600 24
5 Ordinary labour Ordinary labour 0.28 no 550 per day 550 154
6 Ordinary labour Sundries and T & P 1 LS 550 per day 55 55
Sub-Total 673.5
Contractor's Profit 10% 0.1 67.35
Contractor's Overhead Expenses 3.5% 0.035 23.57
Total 764.42
Add VAT with adjustment factor. 1.08108 7.5% 0.075 61.98
Grand Total 826.4
Rate per sft 8.26
Rate per sqm 88.91
Help