Breakup

24.18.1 Providing seal coat with 4 cft of Sylhet sand (FM 2.2) mixed with @ 7.32 kg of bitumen (60/70 penetration grade) per 10 sqm of road surface including supplying and spreading of dry sand (F.M. 0.80) @ 0.09 cum per 10 sqm, including heating bitumen upto 176°C to 190°C, and spreading, rolling at a temperature not below 90°C celsius with appropriate steel drum roller (3 -5 ton) and pneumatic multiple tire roller (8-10 tons) to the desired compaction etc. all complete (cost of bitumen included ) and accepted by the Engineer-in-charge.

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 60/70 grade bitumen for road work Cost of materials : Bitumen (60/70 grade) 15.5 lbs 56000 per M. ton 25.4 393.7
2 Sand (F.M. 2.2) Sylhet sand (F.M. 2.2) 4 cft 5380 per % cft 53.8 215.2
3 Sand (F.M. 0.8) Sand (F.M. 0.8) 3 cft 1670 per % cft 16.7 50.1
4 Fire-wood Fire wood 0.5 mnds 220 per mound 220 110
5 Mason / Mosaic mistry Labour charges: Mason 0.008 no 700 per day 700 5.6
6 Skilled labour Skilled labour 0.05 no 600 per day 600 30
7 Ordinary labour Ordinary labour 0.15 no 550 per day 550 82.5
8 Ordinary labour Sundries and T & P 1 LS 550 per day 55 55
9 Hire charge of vibratory (ride on) roller with 2 steel drum compactor (3-5 tons) Equipment Charges: Hire Charge of Vibratory (Ride On) Roller 2 Steel Drum Compactor (3-5 tons) 0.005 day 5500 per day 5500 27.5
10 Hire charge of pneumatic multiple tired roller (7 tires, 8-10 tons) Hire Charge of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons) 0.005 day 5000 per day 5000 25
11 Diesel Diesel 0.008 liter 68 litre 68 0.54
12 Lubricants Lubricants 0.008 liter 220 per litre 220 1.76
Sub-Total 996.9
Contractor's Profit 10% 0.1 99.69
Contractor's Overhead Expenses 3.5% 0.035 34.89
Total 1131.48
Add VAT with adjustment factor. 1.08108 7.5% 0.075 91.74
Grand Total 1223.22
Rate per sft 12.23
Rate per sqm 131.64
Help