Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Painter Painter | 1 | no | 700 | per day | 700 | 700 | |
| 2 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| 3 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter | 1 | no | 550 | per day | 550 | 550 | |
| 4 | Premium synthetic enamel paint Synthetic enamel Paint | 1.5 | liter | 290 | per litre | 290 | 435 | |
| 5 | Textured coating including sealer, texture coat & top coat Sealer | 1 | liter | 270 | per litre | 270 | 270 | |
| 6 | Thinner for oil-based paint (turpentine) for general purpose Thinner | 1 | liter | 130 | per litre | 130 | 130 | |
| 7 | Ordinary labour T & P local carriege Sundries | 1 | LS | 550 | per day | 171.88 | 171.88 | |
| Sub-Total | 2806.88 | |||||||
| Contractor's Profit | 10% | 0.1 | 280.69 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 98.24 | |||||
| Total | 3185.81 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 258.31 | ||||
| Grand Total | 3444.12 | |||||||
| Rate per sft | 34.44 | |||||||
| Rate per sqm | 370.71 | |||||||