Breakup

24.21 Providing expansion joints across the R.C.C. road pavement with 20 mm gap between the adjacent panels. Supplying dowel bars of size 12 mm dia and 600 mm long M.S rod placed @ 750 mm c/c. 300 mm of the bar being fixed within one slab keeping remaining portion the bar free within the adjacent slab being inserted in 20 mm dia and 300 mm long P.V.C. pipe embedded in the slab, inside of pipe fully greased, filling the gap between the slabs (with admixture) of hot bitumen and coarse sand (F.M. 2.2) in proportion of 2:1, finishing the top with bitumen, spreading coarse sand over the joint, all complete as per plan, drawing and accepted by the Engineer-in-charge.

Considering 10 rft long expansion joint

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Grade 400/420(400Mpa / 400N/mm2 ≈ 60900psi/ 60 Grade), BDS-6935-2006, B400: and ratio fy to fu => 1.25 (a)Cost of materials: (i)1/2"dia M.S. rod:@0.67lbs per rft 4x2'-0"=8rft=5.63lbs 5.63 lbs 72000 per M. ton 32.65 183.82
2 Roof grade 3/4"/19 mm dia pipe, 1.5mm thick (ii)3/4"dia PVC pipe 4x1'-0"=4rft 4 rft 6.5 per foot 6.5 26
3 Ordinary labour (iii) Greese 1 LS 550 per day 55 55
4 60/70 grade bitumen for road work (iv) Bitumen 6.6 lbs 56000 per M. ton 25.4 167.64
5 Sand (F.M. 2.2) Sand (F.M. 2.2) 0.208 cft 5380 per % cft 53.8 11.19
6 Rod binder Labour charges: Rod binder 0.2 no 700 per day 700 140
7 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to rod binder 0.5 no 550 per day 550 275
8 Ordinary labour Ordinary Labour 0.2 no 550 per day 550 110
Sub-Total 968.65
Contractor's Profit 10% 0.1 96.87
Contractor's Overhead Expenses 3.5% 0.035 33.9
Total 1099.42
Add VAT with adjustment factor. 1.08108 7.5% 0.075 89.14
Grand Total 1188.56
Rate per rft 118.9
Rate per rm 390.11
Help