Considering 10 rft long expansion joint
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Grade 400/420(400Mpa / 400N/mm2 ≈ 60900psi/ 60 Grade), BDS-6935-2006, B400: and ratio fy to fu => 1.25 (a)Cost of materials: (i)1/2"dia M.S. rod:@0.67lbs per rft 4x2'-0"=8rft=5.63lbs | 5.63 | lbs | 72000 | per M. ton | 32.65 | 183.82 | |
| 2 | Roof grade 3/4"/19 mm dia pipe, 1.5mm thick (ii)3/4"dia PVC pipe 4x1'-0"=4rft | 4 | rft | 6.5 | per foot | 6.5 | 26 | |
| 3 | Ordinary labour (iii) Greese | 1 | LS | 550 | per day | 55 | 55 | |
| 4 | 60/70 grade bitumen for road work (iv) Bitumen | 6.6 | lbs | 56000 | per M. ton | 25.4 | 167.64 | |
| 5 | Sand (F.M. 2.2) Sand (F.M. 2.2) | 0.208 | cft | 5380 | per % cft | 53.8 | 11.19 | |
| 6 | Rod binder Labour charges: Rod binder | 0.2 | no | 700 | per day | 700 | 140 | |
| 7 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to rod binder | 0.5 | no | 550 | per day | 550 | 275 | |
| 8 | Ordinary labour Ordinary Labour | 0.2 | no | 550 | per day | 550 | 110 | |
| Sub-Total | 968.65 | |||||||
| Contractor's Profit | 10% | 0.1 | 96.87 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 33.9 | |||||
| Total | 1099.42 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 89.14 | ||||
| Grand Total | 1188.56 | |||||||
| Rate per rft | 118.9 | |||||||
| Rate per rm | 390.11 | |||||||