Considering 200 cft soil
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 2 | Ordinary labour Add for each addl. floor for 6th floor to 9th floor (@ 0.5 no lab. per % cft) | 1 | - | 550 | per day | 119.16 | 119.16 | |
| Sub-Total | 119.16 | |||||||
| Contractor's Profit | 10% | 0.1 | 11.92 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 4.17 | |||||
| Total | 135.25 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 10.97 | ||||
| Grand Total | 146.22 | |||||||
| Rate per cft | 0.73 | |||||||
| Rate per cum | 25.78 | |||||||