Breakup

26.01.1 Approx. 670~690 X 360~ 362 mm size, minimum 27.5 kg of weight; Equivalent to Stella:Victoria /Stella: Imola / RAK: Amy / RAK: Karla or similar brand

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
8 Approx. 670~690 X 360~ 362 mm size, minimum 27.5 kg of weight; Equivalent to Stella:Victoria /Stella: Imola / RAK: Karla or similar brand Material cost: (A) Combi closet 1 no 6075 each 6075 6075
9 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Installation cost: (B) Fitting fixing materials: Cement mortar (1:4) (i) Cement 0.1 bag 410 per bag 410 41
10 Sand (F.M. 1.2) (ii) Sand (F.M. 1.2) 0.5 cft 1900 per % cft 19 9.5
11 Nuts with washer Nuts with washer 4 nos 30 each 30 120
12 Plumber Labour : Plumber 0.25 no 700 per day 700 175
13 Skilled labour Skilled labour 1 no 600 per day 600 600
14 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
Sub-Total 7295.5
Contractor's Profit 10% 0.1 729.55
Contractor's Overhead Expenses 3.5% 0.035 255.34
Total 8280.39
Add VAT with adjustment factor. 1.08108 7.5% 0.075 671.38
Grand Total 8951.77
Rate per no 8952
Rate per no 8952