Breakup

26.01.4 Approx. 670~670 X 350~390 mm size, minimum 25.2 kg of weight, Equivalent to COTTO :C1480 /COTTO: C13960 / RAK Series 600 or similar brand

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
5 Approx. 670~670 X 350~390 mm size, minimum 25.2 kg of weight, Equivalent to COTTO: C13960 / RAK Series 600 or similar brand Material cost: (A) Combi closet 1 no 9580 each 9580 9580
6 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Installation cost: (B) Fitting fixing materials:Cement mortar (1:4): Cement 0.1 bag 410 per bag 410 41
7 Sand (F.M. 1.2) Sand (F.M. 1.2) 0.5 cft 1900 per % cft 19 9.5
8 Nuts with washer Nuts with washer 4 nos 30 each 30 120
9 Plumber Labour: Plumber 0.25 no 700 per day 700 175
10 Skilled labour Skilled labour 1 no 600 per day 600 600
11 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
Sub-Total 10800.5
Contractor's Profit 10% 0.1 1080.05
Contractor's Overhead Expenses 3.5% 0.035 378.02
Total 12258.57
Add VAT with adjustment factor. 1.08108 7.5% 0.075 993.94
Grand Total 13252.51
Rate per each 13253
Rate per each 13253