Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 5 | Approx. 668~750 x 356 ~430 mm size, minimum 37 .0 kg of weight, Equivalent to Stella:Isabella /RAK: Washington / RAK: Jumairah or similar brand Material cost: (A) Combi closet | 1 | no | 11703 | each | 11703 | 11703 | |
| 6 | Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Installation cost: (B) Fitting fixing materials:Cement mortar (1:4): Cement | 0.1 | bag | 410 | per bag | 410 | 41 | |
| 7 | Sand (F.M. 1.2) Sand (F.M. 1.2) | 0.5 | cft | 1900 | per % cft | 19 | 9.5 | |
| 8 | Nuts with washer Nuts with washer | 4 | nos | 30 | each | 30 | 120 | |
| 9 | Plumber Labour: Plumber | 0.25 | no | 700 | per day | 700 | 175 | |
| 10 | Skilled labour Skilled labour | 1 | no | 600 | per day | 600 | 600 | |
| 11 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| Sub-Total | 12923.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 1292.35 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 452.32 | |||||
| Total | 14668.17 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1189.31 | ||||
| Grand Total | 15857.48 | |||||||
| Rate per each | 15857 | |||||||
| Rate per each | 15857 | |||||||