Breakup

26.02.2 Approx. 685~729 X 360~406 mm size, minimum 36.0 kg of weight; Equivalent RAK: Oasis/Stella: Evana/ Stella: Marlina or equivalent model

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Approx. 685~729 X 360~406 mm size, minimum 36.0 kg of weight; Equivalent RAK: Oasis/Stella: Evana/ Stella: Marlina or equivalent model Material cost: (A) Combi closet 1 no 16500 each 16500 16500
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Installation cost: (B) Fitting fixing materials:Cement mortar (1:4): Cement 0.1 bag 410 per bag 410 41
3 Sand (F.M. 1.2) Sand (F.M. 1.2) 0.5 cft 1900 per % cft 19 9.5
4 Nuts with washer Nuts with washer 4 nos 30 each 30 120
5 Plumber Labour: Plumber 0.25 no 700 per day 700 175
6 Skilled labour Skilled labour 0.5 no 600 per day 600 300
7 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
Sub-Total 17420.5
Contractor's Profit 10% 0.1 1742.05
Contractor's Overhead Expenses 3.5% 0.035 609.72
Total 19772.27
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1603.16
Grand Total 21375.43
Rate per each 21375
Rate per each 21375