Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Approx. 715~735 X 280~480 mm size, minimum 39.5 kg of weight; Equivalent to COTTO - C1053 / COTTO: 1141 / CHARU: CM 950 / RAK: Galaxy or similar brand Material cost: (A) Combi closet | 1 | no | 20000 | each | 20000 | 20000 | |
| 2 | Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Installation cost: (B) Fitting fixing materials:Cement mortar (1:4): Cement | 0.1 | bag | 410 | per bag | 410 | 41 | |
| 3 | Sand (F.M. 1.2) Sand (F.M. 1.2) | 0.5 | cft | 1900 | per % cft | 19 | 9.5 | |
| 4 | Nuts with washer Nuts with washer | 4 | nos | 30 | each | 30 | 120 | |
| 5 | Plumber Labour: Plumber | 0.25 | no | 700 | per day | 700 | 175 | |
| 6 | Skilled labour Skilled labour | 0.5 | no | 600 | per day | 600 | 300 | |
| 7 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| Sub-Total | 20920.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 2092.05 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 732.22 | |||||
| Total | 23744.77 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1925.25 | ||||
| Grand Total | 25670.02 | |||||||
| Rate per each | 25670 | |||||||
| Rate per each | 25670 | |||||||