Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | approx. 380 mm x 710 mm x 800 mm size, 28.00 kg of weight (flush valve) Material cost: (A) Combi closet | 1 | no | 20700 | each | 20700 | 20700 | |
| 3 | Plumber Labour: Plumber | 0.25 | no | 700 | per day | 700 | 175 | |
| 4 | Skilled labour Skilled labour | 0.5 | no | 600 | per day | 600 | 300 | |
| 5 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| 2 | Installation cost: (B) Fitting fixing materials: Screw, rowel plug, washer, putty etc. | LS | 75 | |||||
| Sub-Total | 21525 | |||||||
| Contractor's Profit | 10% | 0.1 | 2152.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 753.38 | |||||
| Total | 24430.88 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1980.88 | ||||
| Grand Total | 26411.76 | |||||||
| Rate per each | 26412 | |||||||
| Rate per each | 26412 | |||||||