Breakup

26.05.2 Approx. 300 X 370 X 510 mm size, minimum 11.0 kg of weight.

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
3 Approx. 300 X 370 X 510 mm size, minimum 11.0 kg of weight. Material cost: (A) Urinal 1 no 2360 each 2360 2360
4 Grating with brass coupling Installation cost: (B)Accessories and fitting fixing materials: Grating with brass coupling 1 no 300 each 300 300
5 32 mm dia PVC waste pipe for W-Basin connection 32 mm dia PVC waste pipe 1 no 360 each 360 360
6 75 mm Screw, Rowel plug & Washer 75 mm rowel plug 2 no 14 each 14 28
7 Plumber Labour: Plumber 0.15 no 700 per day 700 105
8 Skilled labour Skilled labour 0.2 no 600 per day 600 120
9 Ordinary labour Ordinary labour 0.4 no 550 per day 550 220
Sub-Total 3493
Contractor's Profit 10% 0.1 349.3
Contractor's Overhead Expenses 3.5% 0.035 122.26
Total 3964.56
Add VAT with adjustment factor. 1.08108 7.5% 0.075 321.45
Grand Total 4286.01
Rate per each 4286
Rate per each 4286
Help