26.07.1 Approx. 520 X 406.4 X 223.52 mm size, minimum 10.0 kg of weight

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
3 Approx. 520 X 406.4 X 223.52 mm size, minimum 10.0 kg of weight Material cost: (A) long pan with foot rest 1 no 860 each 860 860
4 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Installation cost: (B) Fitting fixing materials: Cement mortar (1:4) : Cement 0.1 bag 410 per bag 410 41
5 Sand (F.M. 1.2) Sand (F.M. 1.2) 0.5 cft 1900 per % cft 19 9.5
6 Plumber Labour: Plumber 0.25 no 700 per day 700 175
7 Skilled labour Skilled labour 0.5 no 600 per day 600 300
8 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
Sub-Total 1660.5
Contractor's Profit 10% 0.1 166.05
Contractor's Overhead Expenses 3.5% 0.035 58.12
Total 1884.67
Add VAT with adjustment factor. 1.08108 7.5% 0.075 152.81
Grand Total 2037.48
Rate per each 2037
Rate per each 2037