04.15 125 mm brick work with first class bricks with cement sand (F.M. 1.2) mortar (1:6) and making bond with connected walls including necessary scaffolding, raking out joints, cleaning and soaking the bricks for at least 24 hours before use and washing of sand, curing at least for 7 days in all floors including cost of water, electricity and other charges etc. all complete and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M) In ground floor

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class/Picked jhama standard bricks Bricks 480 nos 10000 per % 0 nos 10 4800
2 Sand (F.M. 1.2) Sand (F.M. 1.2) 14 cft 1900 per % cft 19 266
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 1.75 bags 410 per bag 410 717.5
4 Head mason / Mosaic head mistry Head mason 0.1 no 800 per day 800 80
5 Mason / Mosaic mistry Mason 0.75 no 700 per day 700 525
6 Skilled labour Skilled labour 0.5 no 600 per day 600 300
7 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
8 Ordinary labour Labour for soaking & cleaning bricks 1 no 550 per day 550 550
9 Ordinary labour Labour for screening & washing sand 0.5 no 550 per day 550 275
10 Ordinary labour Labour for 7 days curing '@ 1/8 No. labour per day 0.875 no 550 per day 550 481.25
11 Scaffolding Scaffolding 25 sft 10 per sft 10 250
12 Ordinary labour Local carriage, storage & sundries etc. 1 LS 550 per day 275 275
Sub-Total 8794.75
Contractor's Profit 10% 0.1 879.48
Contractor's Overhead Expenses 3.5% 0.035 307.82
Total 9982.05
Add VAT with adjustment factor. 1.08108 7.5% 0.075 809.35
Grand Total 10791.4
Rate per sft 107.91