Breakup

Supplying, fitting and fixing of plastic low-down of any color, on walls or directly over water closet with necessary accessories, making holes wherever required and mending good the damages and fitting, fixing & finishing etc. complete with all necessary fittings and connections approved and accepted by the Engineer- in- charge.

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
3 Plastic low down complete Per set including internal fittings Material cost: (A) Plastic low down 1 no 900 each 900 900
4 32 mm dia PVC waste pipe for W-Basin connection Installation cost: (B) Fitting fixing materials: 32 mm dia plastic pipe 1 no 360 each 360 360
5 CI brackets C.I. Bracket 1 pair 150 per pair 150 150
7 PVC connection pipe PVC connection pipe 1 no 45 each 45 45
8 Plumber Labour: Plumber 0.25 no 700 per day 700 175
9 Skilled labour Skilled labour 0.5 no 600 per day 600 300
6 Screw, rowel plug, washer, putty etc. LS 50
Sub-Total 1980
Contractor's Profit 10% 0.1 198
Contractor's Overhead Expenses 3.5% 0.035 69.3
Total 2247.3
Add VAT with adjustment factor. 1.08108 7.5% 0.075 182.21
Grand Total 2429.51
Rate per each 2430
Rate per each 2430