Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Flush valve for urinal Material cost: (A) flush valve for Urinal | 1 | no | 4200 | each | 4200 | 4200 | |
| 2 | Clamp Installation cost: (B) Fitting fixing materials: Clamp | 2 | no | 40 | each | 40 | 80 | |
| 4 | PVC connection pipe PVC connection pipe | 1 | no | 45 | each | 45 | 45 | |
| 5 | Plumber Labour: Plumber | 0.2 | no | 700 | per day | 700 | 140 | |
| 6 | Skilled labour Skilled labour | 0.4 | no | 600 | per day | 600 | 240 | |
| 3 | Screw, rowel plug, washer, putty etc. | LS | 50 | |||||
| Sub-Total | 4755 | |||||||
| Contractor's Profit | 10% | 0.1 | 475.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 166.43 | |||||
| Total | 5396.93 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 437.59 | ||||
| Grand Total | 5834.52 | |||||||
| Rate per each | 5835 | |||||||
| Rate per each | 5835 | |||||||