26.12.9 Table Top: Approx. 480X 370 mm size, minimu weight 10.0 kg

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Table Top: Approx. 480X 370 mm size, minimu weight 10.0 kg Material cost: (A) wash basin ex. pedestal 1 no 3940 each 3940 3940
2 32 mm dia PVC waste pipe for W-Basin connection Installation cost: (B) Accessories: 32 mm dia PVC waste pipe 1 no 360 each 360 360
3 Grating with brass coupling Grating with brass coupling 1 no 300 each 300 300
4 CP chain with rubber plug CP chain with rubber plug 1 no 80 each 80 80
5 CI brackets CI brakets 1 pair 150 per pair 150 150
6 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Fitting fixing materials: Cement mortar (1:4) Cement 0.01 bag 410 per bag 410 4.1
7 Sand (F.M. 1.2) Sand (F.M. 1.2) 0.05 cft 1900 per % cft 19 0.95
8 Plumber Labour: Plumber 0.15 no 700 per day 700 105
9 Skilled labour Skilled labour 0.5 no 600 per day 600 300
10 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
Sub-Total 5515.05
Contractor's Profit 10% 0.1 551.5
Contractor's Overhead Expenses 3.5% 0.035 193.03
Total 6259.58
Add VAT with adjustment factor. 1.08108 7.5% 0.075 507.53
Grand Total 6767.11
Rate per each 6767
Rate per each 6767