Breakup

04.18 Exposed 125 mm thick pointing ornamental brick work with automatic machine made first class bricks with cement sand (F.M. 1.2) mortar (1:4) and making bond with connected walls including necessary scaffolding, raking out joints, cleaning and soaking the bricks for at least 24 hours before use and washing of sand, curing at least for 7 days in all floors including cost of water, electricity and other charges etc. all complete and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M) In ground floor

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Automatic machine made 1st class standard bricks Bricks 480 nos 11500 per % 0 nos 11.5 5520
2 Sand (F.M. 1.2) Sand (F.M. 1.2) in/c wastage 15 cft 1900 per % cft 19 285
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement in/c pointing 3 bags 410 per bag 410 1230
4 Head mason / Mosaic head mistry Head mason 0.1 no 800 per day 800 80
5 Mason / Mosaic mistry Mason 1 no 700 per day 700 700
6 Skilled labour Skilled labour 0.5 no 600 per day 600 300
7 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
8 Ordinary labour Labour for soaking & cleaning bricks 1 no 550 per day 550 550
9 Ordinary labour Labour for screening & washing sand 0.25 no 550 per day 550 137.5
10 Ordinary labour Labour for 7 days curing '@ 1/4 labour per day 1.75 no 550 per day 550 962.5
11 Scaffolding Scaffolding and stageing 25 sft 10 per sft 10 250
12 Ordinary labour Local carriage, storage & sundries etc. 1 LS 550 per day 687.5 687.5
Sub-Total 10977.5
Contractor's Profit 10% 0.1 1097.75
Contractor's Overhead Expenses 3.5% 0.035 384.21
Total 12459.46
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1010.23
Grand Total 13469.69
Rate per sft 134.7
Rate per per sqm 1449.98
Help