Breakup

04.19 Providing 125 mm thick brick work in superstructure (partition walls) with cement sand (F.M. 1.2) mortar (1:4) with 10 hole machine made ceramic bricks of approved size having uniform colour, carefully laid in cement mortar of uniform width & depth of joints, true to vertical and horizontal lines including racking out joints, filling the interstices with same mortar, making bond with connected walls, cleaning, soaking brick at least 24 hours and washing of sand, curing 7 days in all floors, including cost of water, electricity and other charges accepted by the Engineer-in-charge. (Cement: CEM-II/B-M) In ground floor

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class 10 holes machine made 9.5" x 4.5" x 2.75" / 237.5 mm x 112.5 mm x 68.75 mm size ceramic bricks Bricks 480 nos 19900 per % 0 nos 19.9 9552
2 Sand (F.M. 1.2) Sand (F.M. 1.2) 16 cft 1900 per % cft 19 304
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 2.8 bags 410 per bag 410 1148
4 Head mason / Mosaic head mistry Head mason 0.1 no 800 per day 800 80
5 Mason / Mosaic mistry Mason 1 no 700 per day 700 700
6 Skilled labour Skilled labour 0.5 no 600 per day 600 300
7 Ordinary labour Ordinary labour 1 no 550 per day 550 550
8 Ordinary labour Labour for soaking & cleaning bricks 1 no 550 per day 550 550
9 Ordinary labour Labour for screening & washing sand 0.25 no 550 per day 550 137.5
10 Ordinary labour Labour for 7 days curing '@ 1/8 No. labour per day 0.875 nos 550 per day 550 481.25
11 Scaffolding Scaffolding 25 sft 10 per sft 10 250
12 Ordinary labour Local carriage, storage & sundries etc. 1 LS 550 per day 275 275
Sub-Total 14327.75
Contractor's Profit 10% 0.1 1432.78
Contractor's Overhead Expenses 3.5% 0.035 501.47
Total 16262
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1318.54
Grand Total 17580.54
Rate per sft 175.81
Rate per per sqm 1892.51