Breakup

26.14.1 Approx. 510X 400 mm size, minimum weight 15 kg

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Approx. 510X 400 mm size, minimum weight 15 kg Material cost: (A) wash basin half pedestal 1 no 2060 each 2060 2060
2 32 mm dia PVC waste pipe for W-Basin connection Installation cost: (B) Accessories: 32 mm dia PVC waste pipe 1 no 360 each 360 360
3 Grating with brass coupling Grating with brass coupling 1 no 300 each 300 300
4 CP chain with rubber plug CP chain with rubber plug 1 no 80 each 80 80
5 CI brackets CI brakets 1 pair 150 per pair 150 150
6 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Fitting fixing materials: Cement mortar (1:4) Cement 0.01 no 410 per bag 410 4.1
7 Sand (F.M. 1.2) Sand (F.M. 1.2) 0.05 cft 1900 per % cft 19 0.95
8 Plumber Labour: Plumber 0.15 no 700 per day 700 105
9 Skilled labour Skilled labour 0.2 no 600 per day 600 120
10 Ordinary labour Ordinary labour 0.4 no 550 per day 550 220
Sub-Total 3400.05
Contractor's Profit 10% 0.1 340.01
Contractor's Overhead Expenses 3.5% 0.035 119
Total 3859.06
Add VAT with adjustment factor. 1.08108 7.5% 0.075 312.9
Grand Total 4171.96
Rate per each 4172
Rate per each 4172