Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | approx. size of 670 mm x 186 mm x 170 mm Material cost: (A) basin pedestal | 1 | no | 1800 | each | 1800 | 1800 | |
| 2 | 75 mm Screw, Rowel plug & Washer Installation cost: (B) Accessories: 75 mm screw, rowel plug | 1 | no | 14 | each | 14 | 14 | |
| 3 | Plumber Labour: Plumber | 0.1 | no | 700 | per day | 700 | 70 | |
| 4 | Skilled labour Skilled labour | 0.25 | no | 600 | per day | 600 | 150 | |
| Sub-Total | 2034 | |||||||
| Contractor's Profit | 10% | 0.1 | 203.4 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 71.19 | |||||
| Total | 2308.59 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 187.18 | ||||
| Grand Total | 2495.77 | |||||||
| Rate per each | 2496 | |||||||
| Rate per each | 2496 | |||||||