Considering 1 sq. meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Belgium Mirror, 5 mm thickness Material cost: (A) 5 mm thick mirror | 1 | sqm | 1120 | sqm | 1120 | 1120 | |
| 2 | Plastic clip Installation cost: (B) Accessories: Plastic clip | 4 | no | 11 | each | 11 | 44 | |
| 3 | 50 mm screw & rowel plug Rowel plug and screw | 4 | no | 9 | each | 9 | 36 | |
| 4 | Plumber Labour: Plumber | 0.05 | no | 700 | per day | 700 | 35 | |
| 5 | Skilled labour Skilled labour | 0.1 | no | 600 | per day | 600 | 60 | |
| 6 | Ordinary labour Ordinary labour | 0.2 | no | 550 | per day | 550 | 110 | |
| Sub-Total | 1405 | |||||||
| Contractor's Profit | 10% | 0.1 | 140.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 49.18 | |||||
| Total | 1594.68 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 129.3 | ||||
| Grand Total | 1723.98 | |||||||
| Rate per sqm | 1724 | |||||||
| Rate per sqm | 1724 | |||||||