Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 600 x 125 x 5 mm size coloured glass shelf with fancy brackets Material cost: (A) Coloured glass shelf | 1 | each | 1250 | each | 1250 | 1250 | |
| 2 | 50 mm screw & rowel plug Installation cost: (B)Accessories: Rowel plug and screw | 4 | no | 9 | each | 9 | 36 | |
| 3 | Plumber Labour: Plumber | 0.05 | no | 700 | per day | 700 | 35 | |
| 4 | Skilled labour Skilled labour | 0.1 | no | 600 | per day | 600 | 60 | |
| 5 | Ordinary labour Ordinary labour | 0.2 | no | 550 | per day | 550 | 110 | |
| Sub-Total | 1491 | |||||||
| Contractor's Profit | 10% | 0.1 | 149.1 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 52.19 | |||||
| Total | 1692.29 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 137.21 | ||||
| Grand Total | 1829.5 | |||||||
| Rate per each | 1830 | |||||||
| Rate per each | 1830 | |||||||