Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | PVC toilet paper holder Material: (A) Toilet Paper Holder | 1 | no | 180 | each | 180 | 180 | |
| 2 | 50 mm screw & rowel plug Installation cost: (B) Accessories: Rowel plug and screw | 2 | no | 9 | each | 9 | 18 | |
| 3 | Plumber Labour: Plumber | 0.01 | no | 700 | per day | 700 | 7 | |
| 4 | Skilled labour Skilled labour | 0.01 | no | 600 | per day | 600 | 6 | |
| 5 | Ordinary labour Ordinary labour | 0.05 | no | 550 | per day | 550 | 27.5 | |
| Sub-Total | 238.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 23.85 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 8.35 | |||||
| Total | 270.7 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 21.95 | ||||
| Grand Total | 292.65 | |||||||
| Rate per each | 293 | |||||||
| Rate per each | 293 | |||||||